Action Id WS-7
Action Improve the flow of water between La Esperanza Peninsula Cove and San Juan Bay
Schedule Short-term
Status Implemented
Update Update January 2010:  Although this action was completed with the cut of the Península de la Esperanza eastern end, currently a sand spit has been formed that people can even walk over to what is now the Islote La Esperanza.  The SJBEP is in conversations with Ernesto Diaz of the DNER because there is a possibility of attracting funds from Morris Berman Trust for a maintenance dredging in the area

Previous update:  This project has been implemented through the collaboration between DNER, USACE, and SJBEP.  The water quality in La Esperanza has drastically improved and the detachment of that piece of land has created excellent habitat for the Brown Pelican.  Educational efforts have also taken place regarding this action.
Date Created 3/3/2006 9:49:33 AM