 |
|
|
|
To obtain detailed information, please, press
over each "Description" to have a status overview. To obtain further
information click on "press here to view all tasks", located, on the top
and bottom corners of the overview. Finally, press over each task to
review recent updates. Thank you!
|
| >
press here to view all tasks |
| Action Id |
WS-7 |
| Action |
Improve the flow of water between La Esperanza Peninsula Cove and San Juan Bay |
| Schedule |
Short-term |
| Status |
Implemented |
| Update |
Update January 2010: Although this action was completed with the cut of the Península de la Esperanza eastern end, currently a sand spit has been formed that people can even walk over to what is now the Islote La Esperanza. The SJBEP is in conversations with Ernesto Diaz of the DNER because there is a possibility of attracting funds from Morris Berman Trust for a maintenance dredging in the area
Previous update: This project has been implemented through the collaboration between DNER, USACE, and SJBEP. The water quality in La Esperanza has drastically improved and the detachment of that piece of land has created excellent habitat for the Brown Pelican. Educational efforts have also taken place regarding this action.
|
| Date Created |
3/3/2006 9:49:33 AM
|
| Last Update |
1/25/2010 3:20:11 PM
|
| Attachment |
|
| >
press here to view all tasks |
|
|
|
|